![]() |
|||||
Buyers' Guide
System DesignSuccessful design of a compressed air system requires correct sizing all system components. This section provides information for designing the following system components:
Air Compressors Establishing required compressor capacity is challenging in existing plants and could be even more difficult in new installations where there isnt a history of air consumption. A comprehensive study should include the minimum pressure required for the system to operate all plant equipment, and the average, minimum and peak flow of compressed air for different production periods. A list of all uses should include this information for each end use with a load factor applied to determine if the use is continuous or intermittent. Some pneumatic equipment, such as air tools, may be operated only twenty-five percent of the time. Therefore the load factor would be different from a continuous automated process. There may be some operation, which consumes a great amount of air for a relatively short duration of a few minutes. This can often be handled with storage receivers at the point of use. High volume users, which consume a large amount of compressed air for longer periods, such as grit blasting will probably require that an additional air compressor be automatically started to maintain system pressure for the duration of that process. When designing a new air compressor consideration must also be given to:
General Rules
Air Dryers A good rule to save capital costs and energy is to dry compressed air only to the level required for the process. In other words, if a 38°F pressure dewpoint is acceptable, but a small user requires 40°F, do not dry all the air to 40°F. It may require less than 1kW per 100 cfm for a refrigerated dryer to produce a 35-38°F pressure dewpoint, but as much as 3 kW per 100 cfm for a regenerative dryer to provide a 40°F dewpoint. Dryers are rated on the basis of the "three 100s"
Any other conditions require correction factors, which are usually available in the manufacturers catalogs. For example, if the inlet air temperature to a refrigerated air dryer were 120°F, the dryer would be derated by approximately 30%. Apply the same installation considerations to dryers as you would for air compressors. Read the instruction book and pay particular attention to ensure all automatic drain traps are operating. Consider minimum pressure drop when selecting air dryers. Similar considerations should apply to any filters which are in the system. Air Receivers A liberal air receiver and storage capacity should be supplied for the system. The air receivers are intended to serve several important functions. Initially with reciprocating compressors, the receiver (or "tank") was used to damp pulsations and to collect condensate. With the advent of rotary screw compressors, the receiver continues to serve as an important part of compressor and system pressure controls and to address intermittent large demands, which may intermittently be in excess of compressor capacity. In some cases of short duration high volume use, a large air receiver may allow a smaller air compressor to be used and allow the automated controls to improve overall system efficiency. With reciprocating compressors, the rule of thumb was to size the air receiver at one gallon per cfm of compressor capacity. Today with most systems using electric motor driven rotary screw compressors, many of which operate load/unload, three to four gallons per cfm may be necessary to attain any part load efficiency. With natural gas engine driven compressors used as efficient trim machines, or at full load, a rule of two gallons per cfm of compressor capacity may be adequate for most installations. Calculating the actual size for the volume required for a receiver to supply a given cfm is as follows:
T = Time interval in minutes, during which a receiver can supply air without excessive drop in pressure If Cap is greater than C, the resulting negative answer indicates that the air compressor will supply the required load. If the compressor is unloaded or shut down, Cap becomes zero and the receiver must supply the load for "T" minutes. Notes:
Cooling Towers Involve the supplier of the engine-driven package. Some of the information you should provide to the cooling tower representative:
Other considerations:
Heat Recovery Systems Consider heat recovery for process applications. Reciprocating Engines Approximate heat balance
Rotary Screw Compressors
|
|||||